The 10-Stage Solar Journey with SVPL
From application submission to DISCOM net metering and direct DBT subsidy transfer.
Application & Registration
Advisor or Customer submits application with electricity bill and roof capacity requirements.
Document Verification
Electricity bill, Aadhaar, PAN, and rooftop photographs are verified by SVPL operations.
Govt. Portal Submission
Application registered on the National PM Surya Ghar portal under Odisha DISCOM jurisdiction.
Bank Loan Application
Collateral-free low-interest solar financing processed through partnered banks.
Loan Sanction & Approval
Bank releases sanction letter and initial mobilization milestone payment.
Equipment Dispatch & Installation Commenced
Tier-1 Mono PERC panels, inverters, and mounting structures delivered on-site.
Solar Installation Completed
Certified technicians complete mounting, inverter wiring, and safety earthing.
DISCOM JE Inspection & Net Metering
Junior Engineer inspects system, synchronizes bi-directional net meter with grid.
Central & State Subsidy Claims
Commissioning report submitted on National PM Surya Ghar portal and Odisha state renewable portal for DBT subsidy processing.
Subsidies Disbursed & Project Incentives Released
Central DBT (up to ₹78,000) & Odisha State Subsidy (₹60,000) credited into customer bank account; Authorized Partner project incentives credited.